Glencore Kroondal Pty Ltd
1.5 mm HDPE liner installation
Square meters: 10 016m²
Installation of 1.5 mm HDPE Liner - Square meters: 10 016m²
Samancor PCD (Pty) Ltd
PCD Five - GCL X800, 2mm HDPE liner, cuspated drain and smooth liner
Square meters: 89 120m²
Supply and installation project
Grinaker – LTA (Pty) Ltd
Supply & install of 1.5 HDPE
Square meters: 285 365m²
Large-scale liner installation
THE Lining Technologies
Supply, deliver & install of Smooth Geoliner (1.5mm)
Square meters: 155 550m²
Geoliner installation project
G4 Mining and Civils Pty Ltd
2mm HDPE supply and installation
Square meters: 5 500m²
Supply and installation milestone
Glencore Kroondal Pty Ltd
1.5 mm HDPE liner installation
Square meters: 10 016m²
Featured project milestone
Additional Projects
More completed works added after Glencore Kroondal Pty Ltd to extend the timeline.
Ekurhuleni Cell 9 Weltevreden Landfill
Date: June 2024
Client: LETTAM Building & Civils
Construction of Cell 9 landfill facility including GCL, double-textured HDPE liner, smooth HDPE liner, and geotextile installation. Size: 460,000 m²
ARM Machadodorp Composite Liner Project
Date: 2022–2024
Client: ARM Machadodorp
Installation of composite liner systems including 2mm HDPE, 1.5mm HDPE, and cuspated drainage materials. Size: 650,700 m²
Grinaker LTA HDPE Liner Installation
Date: March 2022
Client: Grinaker LTA (Pty) Ltd
Supply and installation of 1.5mm HDPE liner for mining infrastructure. Size: 285,365 m²
Two Rivers Platinum Mine
Date: November 2023
Client: WBHO Construction Civils
Supply and installation of 1.5mm HDPE liner for platinum mining operations. Size: 51,228 m²
Okuncono Projects TMP
Date: November 2023
Client: Okuncono Projects
Supply of HDPE liner systems for industrial containment applications. Size: 126,040 m²
The Lining Technologies Project
Date: September 2023
Client: The Lining Technologies
Supply, delivery, and installation of 1.5mm smooth geoliner systems. Size: 155,550 m²
Glencore Kroondal Pty Ltd
Date: July 2026
Client: Glencore Kroondal Pty Ltd
Installation of 1.5mm HDPE liner for mining containment infrastructure. Size: 10,016 m²
Blue Print uMzimkhulu Landfill Site
Date: November 2018
Client: Blue Print (Pty) Ltd
Installation of 2mm HDPE liner, GCL, and geotextile systems for landfill development. Size: 89,500 m²
Samancor PCD Five
Date: September 2019
Client: Samancor PCD (Pty) Ltd
Installation of GCL X800, 2mm HDPE textured liner, cuspated drain, and smooth HDPE liner system. Size: 89,120 m²
Arnot Mine Project
Date: January 2020
Client: Tseke Construction
Installation of 1.5mm HDPE smooth liner for mining infrastructure. Size: 150,450 m²